Permits we handle here

How long permits take

  • Roof

    4 days

    1 in 10 waits 23 days or more30% issued the same or next day

  • Windows, doors and shutters

    7 days

    1 in 10 waits 53 days or more11% issued the same or next day

  • Fence

    20 days

    1 in 10 waits 114 days or more

  • Air conditioning and heating

    Same day

    1 in 10 waits 26 days or more64% issued the same or next day

  • Solar panels

    16 days

    1 in 10 waits 81 days or more

  • Pool

    3 days

    1 in 10 waits 49 days or more43% issued the same or next day

  • Generator

    36 days

    1 in 10 waits 247 days or more

  • Electrical

    3 days

    1 in 10 waits 57 days or more44% issued the same or next day

  • Plumbing

    1 day

    1 in 10 waits 35 days or more56% issued the same or next day

  • Home remodel or addition

    76 days

    1 in 10 waits 403 days or more

  • New home

    137 days

    1 in 10 waits 538 days or more

  • Commercial remodel

    102 days

    1 in 10 waits 471 days or more

  • New commercial building

    198 days

    1 in 10 waits 847 days or more

  • Demolition

    6 days

    1 in 10 waits 85 days or more36% issued the same or next day

  • Sign

    47 days

    1 in 10 waits 231 days or more

Florida law

  • For an existing single-family home and work under $15,000, the office must approve or deny the permit within 5 business days of a complete application.

    Applies to structural, accessory structure, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing and roofing permits reviewed by the office’s own plans reviewer.

    F.S. 553.792(1)(a)1.

  • If the office misses its deadline, it must cut the permit fee by 10% for each business day late.

    Not if you agreed in writing to more time, if the delay is yours, or if it is caused by force majeure.

    F.S. 553.792(1)(e)

  • Work on a single-family home valued under $7,500 is exempt from a building permit if you ask the office in writing.

    Send the request with the contract or another document showing the work and its value. It does not apply in a flood hazard area, to electrical, plumbing, structural, mechanical or gas work, or to a job split up to stay under the limit.

    F.S. 553.79(1)(g)

  • A permit for a single-family home expires 1 year after it is issued, or when the next edition of the Florida Building Code takes effect, whichever is later.

    The office may extend it, and may send a notice at least 30 days before it expires.

    F.S. 553.79(1)(c)

  • The office may not deny you a permit only because you are listed on other permits that are not closed.

    F.S. 553.79(17)(b)

Miami-Dade County rules

  • Since July 1, 2026, work under $7,500 on a single-family home, duplex or townhouse can go without a building permit if you request the exemption.

    Send a written request and the contract through the county portal. Not in a flood hazard area; units in multifamily buildings do not qualify.

    Miami-Dade, Permit Exemptions (HB 803)

  • Even under $7,500, electrical, plumbing, mechanical, gas and structural work needs a permit, and the county counts windows, doors, wind-resistant fences and sheds as structural.

    Miami-Dade, Permit Exemptions (HB 803)

  • Replacing an electric water heater of up to 50 gallons needs no permit when a licensed plumbing contractor does it.

    Up to 4,500 watts; a new heater that draws more watts than the old one needs a permit. Gas water heaters are not included.

    Miami-Dade, Permit Exemptions IV

  • A licensed roofing contractor may repair or replace roof covering without a permit up to $2,000 and two roofing squares.

    Both limits apply together. Waterproofing roof coatings need a permit.

    Miami-Dade, Permit Exemptions IV

  • An exact air conditioning change-out at the same amperage needs no electrical permit, but it does need a mechanical permit.

    Miami-Dade, Permit Exemptions IV

Find your open permits

Free. No account.

Contractors pulling permits here

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of Miami-Dade County. Permits the county issues itself, mostly in its unincorporated area.