Small jobs under $7,500

  • Since July 1, 2026, work under $7,500 on a single-family home, duplex or townhouse can go without a building permit if you request the exemption.

    Send a written request and the contract through the county portal. Not in a flood hazard area; units in multifamily buildings do not qualify.

    Miami-Dade, Permit Exemptions (HB 803)

  • Even under $7,500, electrical, plumbing, mechanical, gas and structural work needs a permit, and the county counts windows, doors, wind-resistant fences and sheds as structural.

    Miami-Dade, Permit Exemptions (HB 803)

  • Chain-link, picket and other fences that are not wind-resistant need no building permit, but they do need a zoning improvement permit.

    Miami-Dade, Permit Exemptions (HB 803)

  • A project cannot be split into phases to stay under $7,500.

    Miami-Dade, Permit Exemptions (HB 803)

Small work at homes without a permit

  • At single-family homes, duplexes, townhouses and condominium units, the work below needs no permit, up to $5,000 in all in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Replacing a window air conditioner, or installing a ductless range hood.

    Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Installing or repairing rain gutters, and screening in an existing covered patio, balcony or porch.

    Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Repairing or replacing a canvas awning, and building a pergola or trellis without a roof.

    A new awning and a pergola need a zoning improvement permit. Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Installing a chain-link fence that is not a pool barrier needs no building permit.

    It needs a zoning improvement permit.

    Miami-Dade, Permit Exemptions III

  • Concrete slabs outside the house, such as open patios, walkways and pavers, and wood decks 18 inches or less above the ground.

    Screened patio slabs and pool slabs need a permit. Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Resurfacing a pool, when no electrical connection is touched.

    Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • New floor surfaces of carpet, tile, brick or wood, and a new coat of roof maintenance coating over the existing roof.

    Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • An enclosure built only to house an outdoor water heater tank.

    Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Removing a storage shed that has no electrical or plumbing work.

    Counts toward the $5,000 a home can do under these exemptions in any 12 months.

    Miami-Dade, Permit Exemptions III

  • Electrical repairs by a licensed electrical contractor up to $500, and, at any value, replacing 15–20 amp, 120 volt switches and outlets.

    Low-voltage systems in houses, duplexes and townhouses are exempt too, not in condominiums. Any repair of electrical equipment on an existing pool needs a permit.

    Miami-Dade, Permit Exemptions III

Repairs without a permit

  • Replacing an electric water heater of up to 50 gallons needs no permit when a licensed plumbing contractor does it.

    Up to 4,500 watts; a new heater that draws more watts than the old one needs a permit. Gas water heaters are not included.

    Miami-Dade, Permit Exemptions IV

  • An exact air conditioning change-out at the same amperage needs no electrical permit, but it does need a mechanical permit.

    Miami-Dade, Permit Exemptions IV

  • A licensed air conditioning or mechanical contractor may, without a permit, repair ducts and repair or replace a coil, compressor, fan or refrigerant piping inside the equipment.

    Other mechanical repairs are exempt up to $500 of materials and labor.

    Miami-Dade, Permit Exemptions IV

  • A licensed plumbing contractor may, without a permit, repair or replace faucets, toilets, sinks, shut-off valves, garbage disposals, dishwashers and residential pool equipment other than heaters.

    Also gas appliances other than water heaters, an exact change-out of an above-ground LP tank, and irrigation repairs. Other plumbing repairs are exempt up to $500.

    Miami-Dade, Permit Exemptions IV

  • Stopping leaks and clearing stoppages needs no permit; replacing a defective concealed pipe with new material does.

    Miami-Dade, Permit Exemptions I.C

  • Repairing or replacing low-voltage devices under 98 volts, such as phone, television, data, central vacuum, burglar alarm and intercom, needs no permit.

    Nor do wiring to pumps or motors under 1 horsepower and time clocks.

    Miami-Dade, Permit Exemptions IV

  • A licensed roofing contractor may repair or replace roof covering without a permit up to $2,000 and two roofing squares.

    Both limits apply together. Waterproofing roof coatings need a permit.

    Miami-Dade, Permit Exemptions IV

  • Replacing an exterior door slab or a window glass pane needs no permit; replacing the door with its frame, or the whole window, does.

    Interior doors can be repaired or replaced exactly without a permit, unless they serve life safety.

    Miami-Dade, Permit Exemptions IV

  • Stucco resurfacing of existing masonry or concrete walls needs no permit at a house, duplex or townhouse, at any value.

    On other buildings, under $2,000. EIFS, siding and work over metal lath need a permit.

    Miami-Dade, Permit Exemptions IV

  • A licensed building contractor may make repairs up to $500 without a permit, if they are not structural, do not change the use and do not affect life safety.

    Miami-Dade, Permit Exemptions IV

  • Satellite dishes of one meter or less need no permit.

    Miami-Dade, Permit Exemptions V

Outside the building code

  • Replacing kitchen cabinets, vanities or paneling in a home in the same layout needs no permit.

    Plumbing, ventilation or electrical work that is moved or changed needs one.

    Miami-Dade, Permit Exemptions II

  • Interior and exterior painting, and painting a roof, need no permit.

    Waterproofing roof coatings need a permit.

    Miami-Dade, Permit Exemptions II

  • Home playground equipment, such as swings, slides, hoops and above-ground trampolines, needs no permit.

    They must meet zoning setbacks; any electrical service to them needs a permit.

    Miami-Dade, Permit Exemptions II

  • Decorative pools and fishponds under 24 inches deep, or under 250 square feet and 2,250 gallons, need no building permit.

    They need a zoning improvement permit.

    Miami-Dade, Permit Exemptions II

  • Decorative ironwork needs no permit; security bars, iron doors and railings do.

    Miami-Dade, Permit Exemptions II

  • Resurfacing, re-striping or seal coating an existing parking lot needs no building permit.

    It needs a zoning improvement permit, and a building permit if the layout changes or accessibility is required.

    Miami-Dade, Permit Exemptions II