Compare places
Typical wait for a permit, job by job, in up to four places.
| Job | Miami-Dade County, FL | Orlando, FL | Austin, TX |
|---|---|---|---|
| Roof | 4 days | 1 day (Fastest) | 3 days |
| Windows, doors and shutters | 7 days | Not enough permits to measure | 4 days (Fastest) |
| Fence | 20 days (Fastest) | 21 days | Not enough permits to measure |
| Air conditioning and heating | Same day (Fastest) | 1 day | 7 days |
| Solar panels | 16 days | 15 days | 8 days (Fastest) |
| Pool | 3 days (Fastest) | 46 days | 65 days |
| Generator | 36 days | Not enough permits to measure | 5 days (Fastest) |
| Electrical | 3 days | 1 day (Fastest) | 8 days |
| Plumbing | 1 day | Same day (Fastest) | 23 days |
| Home remodel or addition | 76 days | 19 days | 9 days (Fastest) |
| New home | 137 days | 54 days (Fastest) | 54 days (Fastest) |
| Commercial remodel | 102 days | 55 days (Fastest) | 56 days |
| New commercial building | 198 days | 139 days (Fastest) | 143 days |
| Demolition | 6 days (Fastest) | Not enough permits to measure | 16 days |
| Sign | 47 days | 23 days (Fastest) | Not enough permits to measure |
Fastest
Typical wait: half of the permits took longer, half took less. Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in each office’s open records.