Typical wait for a permit, job by job, in up to four places.

Typical wait in days from application to issue, by job and place
JobMiami-Dade County, FLOrlando, FLAustin, TX
Roof4 days1 day (Fastest)3 days
Windows, doors and shutters7 daysNot enough permits to measure4 days (Fastest)
Fence20 days (Fastest)21 daysNot enough permits to measure
Air conditioning and heatingSame day (Fastest)1 day7 days
Solar panels16 days15 days8 days (Fastest)
Pool3 days (Fastest)46 days65 days
Generator36 daysNot enough permits to measure5 days (Fastest)
Electrical3 days1 day (Fastest)8 days
Plumbing1 daySame day (Fastest)23 days
Home remodel or addition76 days19 days9 days (Fastest)
New home137 days54 days (Fastest)54 days (Fastest)
Commercial remodel102 days55 days (Fastest)56 days
New commercial building198 days139 days (Fastest)143 days
Demolition6 days (Fastest)Not enough permits to measure16 days
Sign47 days23 days (Fastest)Not enough permits to measure

Fastest

Typical wait: half of the permits took longer, half took less. Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in each office’s open records.