Fence permit
The permit, the forms and the list for your job.
Updated
How long it takes
The office says
1–2 business days
if nothing is missing
Its records show
20 days, typically
1 in 10 waits 114 days or more.
What every application carries
Permit application
- Signed by: You and the owner
- Notarized
We fill it in
Contact sheet
We fill it in
Fence addendum
We start it; you finish it
Survey with the fence marked
You upload it
Standard detail for your material
Or sealed drawings.
We attach it
The exact forms depend on your fence.See the list for my fence
Sometimes you also need
The fence crosses a utility easement
Sunshine 811 ticket number, on the addendum
Call 1-800-432-4770 and wait four working days before you file. The owner signs the easement part.
You upload it
The owner is building it themselves, or does not appear in the public records
Proof of ownership
Warranty deed, closing statement or tax receipt.
You upload it
A wall goes on the property line shared with a neighbor
The neighboring owner’s letter of approval
You upload it
The property has a homeowners association
Its letter approving the fence
You upload it
We start it; you finish it
The fence goes up to 2 feet over the height limit, behind the front of the house (never in the front yard)
Height affidavit
- Signed by: The neighbors on the sides and at the back
- Notarized
We start it; you finish it
What the reviewers check
- No more than 6 feet high at the front, and 2.5 feet where it blocks the view at an intersection or within 10 feet of either side of a driveway.
- Walls finished with stucco and paint on both sides.
- No chain link on the front building line.
- The finished side faces the neighbor or the street.
- Nothing inside an easement without the utilities’ written consent.
Source: Miami-Dade County. Updated November 16, 2026. Building regulations in Miami-Dade County.