Florida permit rules

In plain words, each rule with the provision it comes from.

Read

How long the office has

  • For an existing single-family home and work under $15,000, the office must approve or deny the permit within 5 business days of a complete application.

    Applies to structural, accessory structure, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing and roofing permits reviewed by the office’s own plans reviewer.

    F.S. 553.792(1)(a)1.

  • For a home under 7,500 square feet, the office has 30 business days from a complete application.

    Covers new homes and their accessory structure, alarm, electrical, irrigation, landscaping, mechanical, plumbing and roofing permits.

    F.S. 553.792(1)(a)2.

  • For a home of 7,500 square feet or more, the office has 60 business days.

    F.S. 553.792(1)(a)3.

  • For signs and commercial buildings under 25,000 square feet, the office has 60 business days.

    F.S. 553.792(1)(a)4.

  • For apartment buildings of up to 50 units, site plans without a public hearing, and lot grading, the office has 60 business days.

    F.S. 553.792(1)(a)5.

  • Within 5 business days of receiving an application, the office must tell you in writing what is missing. If it does not, the application counts as complete.

    F.S. 553.792(1)(c)

  • If the office misses its deadline, it must cut the permit fee by 10% for each business day late.

    Not if you agreed in writing to more time, if the delay is yours, or if it is caused by force majeure.

    F.S. 553.792(1)(e)

  • If the office sends written reasons the application fails the code, you have 10 business days to correct it, and the office then has 10 business days to decide.

    If the office misses those 10 days, the fee drops 20% for each business day late.

    F.S. 553.792(1)(f)–(g)

  • The office may not make you waive these deadlines as a condition of reviewing your application.

    F.S. 553.792(1)(a)7.

When no permit is needed

  • Work on a single-family home valued under $7,500 is exempt from a building permit if you ask the office in writing.

    Send the request with the contract or another document showing the work and its value. It does not apply in a flood hazard area, to electrical, plumbing, structural, mechanical or gas work, or to a job split up to stay under the limit.

    F.S. 553.79(1)(g)

  • Temporary hurricane and flood walls or barriers at a home are exempt from a building permit if you ask the office in writing.

    Installed by a licensed contractor, not habitable or load-bearing, within zoning and setback rules, and not in a flood hazard area.

    F.S. 553.79(1)(h)

Before work starts

  • Before work starts, the owner must record a notice of commencement with the county clerk and post a copy at the job.

    Unless the law exempts the improvement.

    F.S. 713.13(1)(a)

  • If the contract is over $5,000, a copy of the recorded notice of commencement goes to the office before the first inspection.

    The office may not ask for it to apply for or issue the permit. Repairing or replacing an air conditioner under $15,000 is left out.

    F.S. 713.135(1)(e)–(f)

  • The office may not ask for your contract with the owner, or your costs, to accept or issue a permit.

    Inspection fees may not be based on the total cost of the project.

    F.S. 553.79(1)(f)

  • The office must post each permit application and its required attachments online, accept applications electronically, and show the status of every application until the permit is issued.

    F.S. 553.79(1)(b)

Contracts and money

  • A contractor who takes more than 10% of the price up front on a home job must apply for the permits within 30 days and start within 90 days of their issue.

    Unless there is just cause or the owner agreed in writing to longer.

    F.S. 489.126(2)(a)

  • A contractor paid more than the work done on a home may not stop working for any 90-day period without just cause.

    F.S. 489.126(3)(a)

  • Breaking either rule is a crime: a misdemeanor under $1,000, and a felony from $1,000 up.

    F.S. 489.126(5)–(6)

  • A home contract over $2,500 must carry the state’s construction lien notice, in capital bold type, signed and dated by the owner.

    Homes of up to four units.

    F.S. 713.015(1)

  • A home contract over $2,500 must explain the owner’s rights under the Florida Homeowners’ Construction Recovery Fund.

    F.S. 489.1425(1)

  • A contractor without the license the work needs cannot enforce the contract.

    F.S. 489.128(1)

Inspections

  • The office must accept inspection requests electronically, by e-mail, web form or app.

    F.S. 553.79(1)(d)

  • If work fails an inspection and the office does not give the code reason within 5 business days, it must refund 10% of the permit and inspection fees.

    F.S. 553.79(7)(a)

  • Offices may inspect by video when they choose to, except structural inspections of threshold buildings.

    F.S. 553.79(6)

Expiry and closing

  • A permit for a single-family home expires 1 year after it is issued, or when the next edition of the Florida Building Code takes effect, whichever is later.

    The office may extend it, and may send a notice at least 30 days before it expires.

    F.S. 553.79(1)(c)

  • An owner can close an open permit with the original contractor, with another licensed contractor, or as an owner-builder.

    A contractor hired only to close it is not liable for the original contractor’s defects.

    F.S. 553.79(16)(a)

  • An expired permit whose work is substantially complete can be closed without a new permit, under the code in force when it was applied for.

    F.S. 553.79(16)(b)

  • The office may close a permit 6 years after it was issued without a final inspection, if it finds no apparent safety hazard.

    F.S. 553.79(16)(c)

  • The office may not deny a permit to, or fine, a buyer because a previous owner left a permit open.

    F.S. 553.79(17)(a)

  • The office may not deny you a permit only because you are listed on other permits that are not closed.

    F.S. 553.79(17)(b)

Which license does which work

  • A general contractor may contract for any work that needs a contractor’s license.

    F.S. 489.105(3)(a)

  • A building contractor builds commercial and residential buildings of up to three stories, and their accessory structures.

    F.S. 489.105(3)(b)

  • A residential contractor builds, remodels and repairs homes of one to three units, up to two habitable stories.

    F.S. 489.105(3)(c)

  • A roofing contractor is unlimited within the roofing trade.

    F.S. 489.105(3)(e)

  • Air conditioning contractors come in three classes: A is unlimited, B is limited to 25 tons of cooling and 500,000 Btu of heating per system, and C only services systems.

    F.S. 489.105(3)(f)–(h)

  • A mechanical contractor is unlimited in air conditioning, refrigeration, heating and ventilation.

    F.S. 489.105(3)(i)

  • Pools need a pool/spa contractor: commercial for any pool, residential for home pools, and servicing for repair only.

    F.S. 489.105(3)(j)–(l)

  • A plumbing contractor is unlimited within the plumbing trade.

    F.S. 489.105(3)(m)

  • A solar contractor installs and repairs solar water heating, pool solar heating and photovoltaic systems.

    F.S. 489.105(3)(o)

  • Electrical work needs an electrical contractor, licensed under the separate part of the law for electrical and alarm contracting.

    F.S. 489.505(12)

Owners as their own contractor

  • Owners may act as their own contractor on a one- or two-family home they will live in, and on commercial buildings up to $75,000 for their own use.

    They must supervise the work themselves and not sell or rent it; a sale within a year suggests it was built to sell.

    F.S. 489.103(7)(a)1.

  • An owner may finish a permit the listed contractor substantially completed, once the office approves it.

    F.S. 489.103(7)(a)4.

Private providers

  • The owner, or the contractor with the owner’s written authorization, may hire a private provider for plans review or inspections at any time.

    F.S. 553.791(2)(a)

  • When a private provider does the review or inspections, the office must lower the permit fee by what it saves.

    On commercial projects at least 25% of that part of the fee, or 50% if the provider does all of it.

    F.S. 553.791(2)(b), (d)

Roofs and wind

  • Replacing the roof of a site-built house includes a secondary water barrier and stronger roof-deck attachment.

    F.S. 553.844(3)(a)

  • In the wind-borne debris region, replacing the roof of a house valued at $300,000 or more also improves the roof-to-wall connections.

    Only when it can be done for about 15% of the cost of the new roof.

    F.S. 553.844(3)(b)

  • On a roof built to the 2007 code or later, repairing or replacing part of it only requires that part to meet the current code.

    When 25% or more of the roof or roof section is being repaired, replaced or recovered.

    F.S. 553.844(5)

  • In the wind-borne debris region, permitted work of $50,000 or more on a building valued at $750,000 or more must add code opening protection.

    Roof covering work is left out.

    F.S. 553.844(3)(c)

  • A roofer’s ad that invites a homeowner to claim roof damage on insurance must say the owner pays the deductible and that waiving it is a felony.

    Offering gifts, cash or a waived deductible for a claim is prohibited.

    F.S. 489.147(1)–(2)

From the Florida Statutes, 2026 edition, on the Florida Senate’s site. Each rule links to its statute.