ReguMap
Office
Miami-Dade County
Applies to
Unincorporated area
Work
Solar panels

Solar permit

The permit, the forms and the list for your job.

Updated

Where does the system go?

Free. No account.

How long it takes

Its records show

16 days, typically

1 in 10 waits 81 days or more.

What every application carries

  1. Permit application, signed and notarized

    We fill it in

  2. Electrical fee sheet, category 34

    You fill it in

  3. Digitally sealed plans

    You upload it

  4. Owner’s solar disclosure

    You fill it in

The exact forms depend on your solar panels.See the list for my solar panels

Sometimes you also need
  • You want a faster review

    Green building expedited review request

    Solar projects qualify under Section 8-6 of the county code, through the Sustainable Buildings Program form.

    We fill it in

  • The roof under the panels is new or being replaced

    A separate roofing permit

    You upload it

  • The system is worth over $50,000, or the service is 600 amps or more (800 for a business)

    Electrical plans sealed by an electrical engineer

    You upload it

  • The owner is acting as their own contractor

    Owner-builder disclosure statement

    The owner reads it before applying and affirms it at the validation appointment.

    • Signed by: The owner

    You upload it

What the reviewers check
  • The electrical items on the county’s PV inspectors checklist.
  • The county’s rooftop solar guidelines for the High Velocity Hurricane Zone.

Source: Miami-Dade County. Updated November 16, 2026. Building regulations in Miami-Dade County.