Pool

Pool permit

The permit, the forms and the list for your job.

Updated

What pool are you building?

Free. No account.

How long it takes

Its records show

3 days, typically

1 in 10 waits 49 days or more.

What every application carries

  1. Permit application

    With the pool’s square feet.

    We fill it in

  2. Contact sheet

    We fill it in

  3. Signed and sealed pool drawings

    For an in-ground pool.

    You upload it

The exact forms depend on your pool.See the list for my pool

Sometimes you also need
  • The pool is commercial or public

    Health Department receipt letter for the pool operating permit

    You upload it

  • The pool barrier is a new fence or wall

    A building permit for the barrier

    Even chain link or picket needs a building permit when it is a pool barrier.

    You upload it

  • The owner is acting as their own contractor

    Owner-builder disclosure statement

    The owner reads it before applying and affirms it at the validation appointment.

    • Signed by: The owner

    You upload it

What the reviewers check
  • A permanent barrier around every new pool, spa or hot tub, at least 48 inches high measured on the side away from the pool.
  • The pool barrier, in its own inspection (code 076).
  • Pool lights meet the low-voltage rule when an existing light is repaired or changed.

Source: Miami-Dade County. Updated November 16, 2026. Building regulations in Miami-Dade County.