Permits we handle here

How long permits take

  • Roof

    16 days

    1 in 10 waits 70 days or more

  • Windows, doors and shutters

    36 days

    1 in 10 waits 145 days or more

  • Fence

    71 days

    1 in 10 waits 245 days or more

  • Air conditioning and heating

    46 days

    1 in 10 waits 570 days or more39% issued the same or next day

  • Water heater

    Same day

    1 in 10 waits 5 days or more82% issued the same or next day

  • Solar panels

    35 days

    1 in 10 waits 121 days or more

  • Pool

    105 days

    1 in 10 waits 340 days or more

  • Generator

    32 days

    1 in 10 waits 268 days or more

  • Demolition

    140 days

    1 in 10 waits 515 days or more

  • Sign

    133 days

    1 in 10 waits 357 days or more

Florida law

  • For an existing single-family home and work under $15,000, the office must approve or deny the permit within 5 business days of a complete application.

    Applies to structural, accessory structure, alarm, electrical, gas, irrigation, landscaping, mechanical, plumbing and roofing permits reviewed by the office’s own plans reviewer.

    F.S. 553.792(1)(a)1.

  • If the office misses its deadline, it must cut the permit fee by 10% for each business day late.

    Not if you agreed in writing to more time, if the delay is yours, or if it is caused by force majeure.

    F.S. 553.792(1)(e)

  • Work on a single-family home valued under $7,500 is exempt from a building permit if you ask the office in writing.

    Send the request with the contract or another document showing the work and its value. It does not apply in a flood hazard area, to electrical, plumbing, structural, mechanical or gas work, or to a job split up to stay under the limit.

    F.S. 553.79(1)(g)

  • A permit for a single-family home expires 1 year after it is issued, or when the next edition of the Florida Building Code takes effect, whichever is later.

    The office may extend it, and may send a notice at least 30 days before it expires.

    F.S. 553.79(1)(c)

  • The office may not deny you a permit only because you are listed on other permits that are not closed.

    F.S. 553.79(17)(b)

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Miami.