How long permits take

  • Home remodel or addition

    25 days

    1 in 10 waits 169 days or more25% issued the same or next day

  • New home

    177 days

    1 in 10 waits 484 days or more

  • Commercial remodel

    45 days

    1 in 10 waits 223 days or more

  • New commercial building

    181 days

    1 in 10 waits 414 days or more

  • Demolition

    92 days

    1 in 10 waits 323 days or more

Find your open permits

Free. No account.

Contractors pulling permits here

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Seattle. Building permits. Electrical and trade permits are published apart and are not counted here.