Permits · WA
Seattle
How long permits take
Home remodel or addition
25 days
1 in 10 waits 169 days or more25% issued the same or next day
New home
177 days
1 in 10 waits 484 days or more
Commercial remodel
45 days
1 in 10 waits 223 days or more
New commercial building
181 days
1 in 10 waits 414 days or more
Demolition
92 days
1 in 10 waits 323 days or more
Find your open permits
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Seattle. Building permits. Electrical and trade permits are published apart and are not counted here.