ReguMap
Place
San Francisco, CA
Records
City and County of San Francisco, Department of Building Inspection

Permits · CA

San Francisco

How long permits take

  • Roof

    Same day

    1 in 10 waits 22 days or more75% issued the same or next day

  • Windows, doors and shutters

    8 days

    1 in 10 waits 259 days or more36% issued the same or next day

  • Fence

    63 days

    1 in 10 waits 405 days or more17% issued the same or next day

  • Solar panels

    55 days

    1 in 10 waits 156 days or more

  • Pool

    33 days

    1 in 10 waits 213 days or more

  • Home remodel or addition

    Same day

    1 in 10 waits 106 days or more58% issued the same or next day

  • New home

    441 days

    1 in 10 waits 1939 days or more

  • Commercial remodel

    11 days

    1 in 10 waits 119 days or more30% issued the same or next day

  • Demolition

    97 days

    1 in 10 waits 1001 days or more

  • Sign

    20 days

    1 in 10 waits 281 days or more24% issued the same or next day

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City and County of San Francisco, Department of Building Inspection. Building permits; electrical and plumbing permits are published apart.