How long permits take

  • Pool

    22 days

    1 in 10 waits 83 days or more

  • Home remodel or addition

    18 days

    1 in 10 waits 83 days or more

  • New home

    53 days

    1 in 10 waits 149 days or more

  • Commercial remodel

    55 days

    1 in 10 waits 233 days or more

  • New commercial building

    111 days

    1 in 10 waits 316 days or more

Find your open permits

Free. No account.

Contractors pulling permits here

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Raleigh. Building permits; the city publishes its trade permits without the application date.