- Place
- Norfolk, VA
- Records
- City of Norfolk
Permits · VA
Norfolk
How long permits take
Roof
3 days
1 in 10 waits 21 days or more32% issued the same or next day
Air conditioning and heating
1 day
1 in 10 waits 9 days or more61% issued the same or next day
Electrical
1 day
1 in 10 waits 8 days or more67% issued the same or next day
Plumbing
1 day
1 in 10 waits 7 days or more70% issued the same or next day
Home remodel or addition
16 days
1 in 10 waits 98 days or more11% issued the same or next day
New home
49 days
1 in 10 waits 221 days or more
Commercial remodel
33 days
1 in 10 waits 151 days or more
New commercial building
28 days
1 in 10 waits 503 days or more14% issued the same or next day
Demolition
4 days
1 in 10 waits 45 days or more32% issued the same or next day
Sign
13 days
1 in 10 waits 42 days or more
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Norfolk.