How long permits take

  • Roof

    3 days

    1 in 10 waits 21 days or more32% issued the same or next day

  • Air conditioning and heating

    1 day

    1 in 10 waits 9 days or more61% issued the same or next day

  • Electrical

    1 day

    1 in 10 waits 8 days or more67% issued the same or next day

  • Plumbing

    1 day

    1 in 10 waits 7 days or more70% issued the same or next day

  • Home remodel or addition

    16 days

    1 in 10 waits 98 days or more11% issued the same or next day

  • New home

    49 days

    1 in 10 waits 221 days or more

  • Commercial remodel

    33 days

    1 in 10 waits 151 days or more

  • New commercial building

    28 days

    1 in 10 waits 503 days or more14% issued the same or next day

  • Demolition

    4 days

    1 in 10 waits 45 days or more32% issued the same or next day

  • Sign

    13 days

    1 in 10 waits 42 days or more

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Norfolk.