How long permits take

  • Roof

    8 days

    1 in 10 waits 37 days or more

  • Air conditioning and heating

    5 days

    1 in 10 waits 40 days or more29% issued the same or next day

  • Solar panels

    24 days

    1 in 10 waits 77 days or more10% issued the same or next day

  • Pool

    28 days

    1 in 10 waits 168 days or more

  • Generator

    12 days

    1 in 10 waits 52 days or more

  • Electrical

    11 days

    1 in 10 waits 71 days or more

  • Plumbing

    3 days

    1 in 10 waits 20 days or more37% issued the same or next day

  • Home remodel or addition

    35 days

    1 in 10 waits 168 days or more

  • New home

    65 days

    1 in 10 waits 280 days or more

  • Demolition

    25 days

    1 in 10 waits 171 days or more

  • Sign

    42 days

    1 in 10 waits 207 days or more

Find your open permits

Free. No account.

Contractors pulling permits here

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of New Orleans.