- Metropolitan Government of Nashville and Davidson County, Codes Administration
Permits · TN
Nashville
How long permits take
Roof
11 days
1 in 10 waits 62 days or more10% issued the same or next day
Pool
26 days
1 in 10 waits 116 days or more
Home remodel or addition
13 days
1 in 10 waits 70 days or more12% issued the same or next day
New home
35 days
1 in 10 waits 175 days or more
Commercial remodel
75 days
1 in 10 waits 262 days or more
New commercial building
108 days
1 in 10 waits 318 days or more
Demolition
14 days
1 in 10 waits 71 days or more
Sign
14 days
1 in 10 waits 105 days or more12% issued the same or next day
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of Metropolitan Government of Nashville and Davidson County, Codes Administration. Building permits across Nashville and Davidson County; trade permits are not published with them.