Montgomery County, MD
Records
Montgomery County, Department of Permitting Services

Permits · MD

Montgomery County

How long permits take

  • Air conditioning and heating

    Same day

    1 in 10 waits 9 days or more78% issued the same or next day

  • Solar panels

    Same day

    1 in 10 waits 0 days or more96% issued the same or next day

  • Pool

    35 days

    1 in 10 waits 183 days or more

  • Generator

    10 days

    1 in 10 waits 52 days or more20% issued the same or next day

  • Electrical

    Same day

    1 in 10 waits 3 days or more89% issued the same or next day

  • Home remodel or addition

    16 days

    1 in 10 waits 85 days or more19% issued the same or next day

  • New home

    50 days

    1 in 10 waits 196 days or more

  • Commercial remodel

    88 days

    1 in 10 waits 217 days or more

  • New commercial building

    178 days

    1 in 10 waits 476 days or more

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of Montgomery County, Department of Permitting Services. Building, electrical and mechanical permits the county issues; some cities, such as Rockville and Gaithersburg, issue their own.