Permits · AZ
Mesa
How long permits take
Solar panels
18 days
1 in 10 waits 39 days or more
Pool
20 days
1 in 10 waits 43 days or more
Electrical
13 days
1 in 10 waits 44 days or more13% issued the same or next day
Plumbing
18 days
1 in 10 waits 46 days or more
Home remodel or addition
47 days
1 in 10 waits 169 days or more
New home
17 days
1 in 10 waits 168 days or more
Commercial remodel
75 days
1 in 10 waits 167 days or more
Find your open permits
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Mesa.