- Place
- Los Angeles, CA
- Records
- City of Los Angeles, Department of Building and Safety
Permits · CA
Los Angeles
How long permits take
Roof
24 days
1 in 10 waits 179 days or more17% issued the same or next day
Windows, doors and shutters
21 days
1 in 10 waits 151 days or more23% issued the same or next day
Fence
100 days
1 in 10 waits 296 days or more12% issued the same or next day
Solar panels
91 days
1 in 10 waits 673 days or more14% issued the same or next day
Pool
35 days
1 in 10 waits 238 days or more24% issued the same or next day
Generator
112 days
1 in 10 waits 354 days or more
Home remodel or addition
48 days
1 in 10 waits 314 days or more18% issued the same or next day
New home
166 days
1 in 10 waits 855 days or more
Commercial remodel
87 days
1 in 10 waits 358 days or more
New commercial building
304 days
1 in 10 waits 1311 days or more
Demolition
95 days
1 in 10 waits 496 days or more
Sign
49 days
1 in 10 waits 186 days or more
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Los Angeles, Department of Building and Safety. Building, pool, demolition and sign permits. Electrical, plumbing and HVAC permits are published apart and are not counted here.