City of Los Angeles, Department of Building and Safety

Permits · CA

Los Angeles

How long permits take

  • Roof

    24 days

    1 in 10 waits 179 days or more17% issued the same or next day

  • Windows, doors and shutters

    21 days

    1 in 10 waits 151 days or more23% issued the same or next day

  • Fence

    100 days

    1 in 10 waits 296 days or more12% issued the same or next day

  • Solar panels

    91 days

    1 in 10 waits 673 days or more14% issued the same or next day

  • Pool

    35 days

    1 in 10 waits 238 days or more24% issued the same or next day

  • Generator

    112 days

    1 in 10 waits 354 days or more

  • Home remodel or addition

    48 days

    1 in 10 waits 314 days or more18% issued the same or next day

  • New home

    166 days

    1 in 10 waits 855 days or more

  • Commercial remodel

    87 days

    1 in 10 waits 358 days or more

  • New commercial building

    304 days

    1 in 10 waits 1311 days or more

  • Demolition

    95 days

    1 in 10 waits 496 days or more

  • Sign

    49 days

    1 in 10 waits 186 days or more

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Los Angeles, Department of Building and Safety. Building, pool, demolition and sign permits. Electrical, plumbing and HVAC permits are published apart and are not counted here.