Cincinnati, OH
Records
City of Cincinnati

Permits · OH

Cincinnati

How long permits take

  • Air conditioning and heating

    5 days

    1 in 10 waits 49 days or more32% issued the same or next day

  • Plumbing

    7 days

    1 in 10 waits 16 days or more

  • Home remodel or addition

    16 days

    1 in 10 waits 105 days or more34% issued the same or next day

  • New home

    64 days

    1 in 10 waits 294 days or more

  • Commercial remodel

    26 days

    1 in 10 waits 151 days or more29% issued the same or next day

  • New commercial building

    244 days

    1 in 10 waits 349 days or more

  • Demolition

    47 days

    1 in 10 waits 167 days or more

  • Sign

    30 days

    1 in 10 waits 127 days or more24% issued the same or next day

Find your open permits

Free. No account.

Contractors pulling permits here

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Cincinnati.