Permits · OH
Cincinnati
How long permits take
Air conditioning and heating
5 days
1 in 10 waits 49 days or more32% issued the same or next day
Plumbing
7 days
1 in 10 waits 16 days or more
Home remodel or addition
16 days
1 in 10 waits 105 days or more34% issued the same or next day
New home
64 days
1 in 10 waits 294 days or more
Commercial remodel
26 days
1 in 10 waits 151 days or more29% issued the same or next day
New commercial building
244 days
1 in 10 waits 349 days or more
Demolition
47 days
1 in 10 waits 167 days or more
Sign
30 days
1 in 10 waits 127 days or more24% issued the same or next day
Find your open permits
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Cincinnati.