How long permits take

  • Roof

    1 day

    1 in 10 waits 14 days or more60% issued the same or next day

  • Windows, doors and shutters

    3 days

    1 in 10 waits 26 days or more37% issued the same or next day

  • Fence

    1 day

    1 in 10 waits 13 days or more57% issued the same or next day

  • Air conditioning and heating

    10 days

    1 in 10 waits 48 days or more18% issued the same or next day

  • Water heater

    3 days

    1 in 10 waits 15 days or more34% issued the same or next day

  • Solar panels

    9 days

    1 in 10 waits 27 days or more

  • Pool

    56 days

    1 in 10 waits 301 days or more

  • Generator

    15 days

    1 in 10 waits 32 days or more11% issued the same or next day

  • Electrical

    1 day

    1 in 10 waits 16 days or more55% issued the same or next day

  • Plumbing

    7 days

    1 in 10 waits 39 days or more22% issued the same or next day

  • New home

    91 days

    1 in 10 waits 268 days or more

  • Demolition

    51 days

    1 in 10 waits 121 days or more28% issued the same or next day

  • Sign

    39 days

    1 in 10 waits 160 days or more

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Chicago.