How long permits take

  • Roof

    Same day

    1 in 10 waits 7 days or more70% issued the same or next day

  • Fence

    8 days

    1 in 10 waits 97 days or more11% issued the same or next day

  • Air conditioning and heating

    1 day

    1 in 10 waits 33 days or more53% issued the same or next day

  • Water heater

    Same day

    1 in 10 waits 4 days or more85% issued the same or next day

  • Pool

    14 days

    1 in 10 waits 64 days or more

  • Generator

    5 days

    1 in 10 waits 36 days or more21% issued the same or next day

  • Electrical

    Same day

    1 in 10 waits 4 days or more82% issued the same or next day

  • Plumbing

    1 day

    1 in 10 waits 8 days or more68% issued the same or next day

  • Home remodel or addition

    23 days

    1 in 10 waits 129 days or more12% issued the same or next day

  • New home

    15 days

    1 in 10 waits 103 days or more

  • Commercial remodel

    53 days

    1 in 10 waits 176 days or more

  • New commercial building

    104 days

    1 in 10 waits 695 days or more

  • Demolition

    Same day

    1 in 10 waits 7 days or more75% issued the same or next day

  • Sign

    4 days

    1 in 10 waits 44 days or more27% issued the same or next day

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Baton Rouge and Parish of East Baton Rouge. Permits the city-parish issues, across East Baton Rouge Parish outside Baker, Central and Zachary.