How long permits take

  • Roof

    3 days

    1 in 10 waits 14 days or more45% issued the same or next day

  • Windows, doors and shutters

    4 days

    1 in 10 waits 38 days or more37% issued the same or next day

  • Air conditioning and heating

    7 days

    1 in 10 waits 197 days or more10% issued the same or next day

  • Water heater

    4 days

    1 in 10 waits 13 days or more21% issued the same or next day

  • Solar panels

    8 days

    1 in 10 waits 223 days or more

  • Pool

    65 days

    1 in 10 waits 343 days or more

  • Generator

    5 days

    1 in 10 waits 140 days or more10% issued the same or next day

  • Electrical

    8 days

    1 in 10 waits 153 days or more14% issued the same or next day

  • Plumbing

    23 days

    1 in 10 waits 311 days or more11% issued the same or next day

  • Home remodel or addition

    9 days

    1 in 10 waits 140 days or more28% issued the same or next day

  • New home

    54 days

    1 in 10 waits 295 days or more

  • Commercial remodel

    56 days

    1 in 10 waits 334 days or more

  • New commercial building

    143 days

    1 in 10 waits 1183 days or more12% issued the same or next day

  • Demolition

    16 days

    1 in 10 waits 121 days or more

Find your open permits

Free. No account.

Contractors pulling permits here

Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Austin.