How long permits take
Roof
3 days
1 in 10 waits 14 days or more45% issued the same or next day
Windows, doors and shutters
4 days
1 in 10 waits 38 days or more37% issued the same or next day
Air conditioning and heating
7 days
1 in 10 waits 197 days or more10% issued the same or next day
Water heater
4 days
1 in 10 waits 13 days or more21% issued the same or next day
Solar panels
8 days
1 in 10 waits 223 days or more
Pool
65 days
1 in 10 waits 343 days or more
Generator
5 days
1 in 10 waits 140 days or more10% issued the same or next day
Electrical
8 days
1 in 10 waits 153 days or more14% issued the same or next day
Plumbing
23 days
1 in 10 waits 311 days or more11% issued the same or next day
Home remodel or addition
9 days
1 in 10 waits 140 days or more28% issued the same or next day
New home
54 days
1 in 10 waits 295 days or more
Commercial remodel
56 days
1 in 10 waits 334 days or more
New commercial building
143 days
1 in 10 waits 1183 days or more12% issued the same or next day
Demolition
16 days
1 in 10 waits 121 days or more
Find your open permits
Calendar days from application to issue, for permits issued Nov 17, 2025 to Nov 16, 2026, in the open records of City of Austin.